ICS Weekly Report: September 10, 2021

ICS Weekly Report: September 10, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Sheridan Hills Elementary

Completed week ending Friday,  September 10, 2021

  • Kitchen/Cafeteria/Receiving Site
    • Cafeteria passed final inspections and is now being used for dining
    • Kitchen equipment is being installed and final mechanical and electrical connections are being made
    • Plumbing fixtures and specialties were installed in the Receiving area Toilet room
    • Flooring was installed in the Food Service office
    • Completed roof parapet metal coping
  • Site
    • Continued site clean-up and demobilization
    • Place concrete for stairs at Gym exit tentatively planned for Saturday 9/11

Planned week ending Friday, September 17, 2021

  • Kitchen/Cafeteria/Receiving
    • Complete all remaining work in the Kitchen
    • Final cleaning in the Kitchen
    • Conduct all required City and State (Health Department) inspections to allow for full occupancy of the Kitchen
  • Site
    • Continue site clean-up and demobilization
    • Resume testing and balancing of the HVAC system
    • Contractors to address punchlist items

Richfield Middle School

Completed week ending Friday, September 10, 2021

  • Main Entrance
    • Card readers and push button entrances installed
  • Bathrooms
    • Installed toilet partitions
  • Boiler Room
    • Scheduled start up and training for September 20
  • Best Buy Teen Tech Center 
    • Floor covering installed
  • Continued auditorium HVAC hydronic re-piping

Planned week ending Friday, September 17, 2021

  • Bathrooms
    • Install backordered tile, wait for remaining wall tile
  • Best Buy Teen Tech Center-Music Suite
    • Waiting on shipment of doors week of 9/20
  • Finish auditorium HVAC hydronic re-piping and clear out auditorium foyer

Central Education Center

Completed week ending Friday, September 10, 2021

  • Classroom Wings
    • Completed wall and door frame painting in the 300 wing offices
    • Completed flooring and base in the 300 wing offices
    • Completed all work in the multi-user toilet rooms in the 300 and 400 wings
    • Wold continued conducting punchlist walkthroughs of finished spaces
  • Mech Spaces
    • Continued chilled water piping and connections to mech equipment
    • Continued installing rooftop ductwork.
  • General 
    • Contractor continued general clean-up and demobilization in and around the buidling
    • All-State is in the process of programming the security and intrusions systems

Planned week ending Friday, September 17, 2021

  • Mech Spaces
    • Contractors to continue completing work associated with the building cooling system in preparation for systems start-up on 9/23
    • Continue rooftop ductwork and exhaust fans installation
  • General
    • Complete dishwasher and sink installation the Prep Room
    • Contractors to work to address punchlist items

Download the PDF Report