ICS Weekly Report: February 12, 2021

ICS Weekly Report: February 12, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, February 26, 2021

  • ICS Commissioning was on-site to review open commissioning list items for completion
  • Continued punch list items, and ICS/Wold verified and closed out completed work
  • Contractors continued working to address items noted on the commissioning corrective action log

Planned week ending Friday, March 5, 2021

  • Contractors to continue working to address items noted on the commissioning corrective action log, meeting scheduled for 03/02

Centennial Elementary

Completed week ending Friday, February 26, 2021

  • IEA Commissioning has completed commissioning the building. They will return to complete seasonal cooling testing
  • Contractors continued working IEA Commissioning log items

Planned week ending Friday, March 5, 2021

  • Contractors to continue working to address IEA Commissioning log items

Sheridan Hills Elementary

Completed week ending Friday, February 26, 2021

  • IEA Commissioning has completed commissioning the building for phases completed to date. They will return to continue commissioning during the final phase of construction
  • Contractors continued working to address punch list and IEA Commissioning log items

Planned week ending Friday, March 5, 2021

  • Contractors continue to address punch list and IEA Commissioning log items

Richfield Middle School

Completed week ending Friday, February 26, 2021

  • Second Floor Restrooms
    • Turned over to school for use
  • First Floor Restrooms
    • Started tiling north restrooms
    • Finished tiling south restrooms
    • Started installing toilet fixtures and toilet partitions in south restrooms 
  • Existing Administration Offices/New Special Education Suite
    • Finished ceilings
    • Flooring
  • Existing Music Suite/New Design Lab
    • Installed floor insulation at tiered music room
    • Continued mechanical and electrical rough ins
  • Wood Shop/New Administration/Fab Lab
    • Finished wall framing 
    • Started sheet rocking
    • Continued mechanical electrical rough ins

Planned week ending Friday, March 5, 2021

  • First Floor Restrooms
    • Finish tiling north restrooms
    • Start ceiling grid
    • Finish installing toilet fixtures and toilet partitions in south restrooms and start in north restrooms
  • Existing Administration Offices/New Special Education Suite
    • Finish flooring
    • Final cleaning
    • Wait for casework
  • Existing Music Suite/New Design Lab
    • Pour concrete floor in music room
    • Continue mechanical and electrical rough ins
    • Wall framing
  • Wood Shop/New Administration/Fab Lab
    • Finish sheet rocking
    • Continue mechanical and electrical rough ins

Richfield STEM Elementary

Completed week ending Friday, February 26, 2021

  • ICS was on site to continue commissioning of existing equipment and verify completion of corrections

Planned week ending Friday, March 5, 2021

  • ICS to continue commissioning and verify completion of log items

Richfield Dual Language School

Completed week ending Friday, February 26, 2021

  • Contractors have addressed all items noted on the commissioning corrective action log except for those items that require warm weather to complete (to be completed in the spring)

Planned week ending Friday, March 5, 2021

  • No work planned

Central Education Center

Completed week ending Friday, February 26, 2021

  • Completed installing temporary partitions and fencing
  • Abatement contractor completed material removals in Area A
  • Started architectural, mechanical, and electrical demolition in Areas A and D 
  • Conducted the weekly Construction Progress/Coordination meeting
  • ICS continued gathering information and proposals for new furniture

Planned week ending Friday, March 5, 2021

  • Abatement contractor to complete the removal of (1) boiler in the lower level
  • Continue Demolition in Areas A and D
  • Begin saw-cutting concrete slabs and removal for new underground plumbing
  • Continue receiving and reviewing material submittals

Download PDF Report 