ICS Weekly Report: October 23, 2020

ICS Weekly Report: October 23, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

High School

Completed week ending Friday, October 23, 2020

  • Boiler Room
    • Continued electrical and mechanical piping connections
  • Area P Link
    • Finished carpet and casework installation
    • Installation of vinyl tile flooring in corridors
  • Lower Level Area F Dance Studio and Weight Room
    • Finished weight room flooring
  • Area C 3rd level science rooms
    • Finished setting cabinets and tops
    • Chemical resistant flooring installation underway
  • Area C 3rd level restrooms
    • Finished floor tile and began wall tile installation
  • New Athletic Corridor/Elevator
    • Continued elevator installation
    • Continued mechanical and electrical rough ins

Planned week ending Friday, October 30, 2020

  • Boiler Room
    • Continue electrical and mechanical piping connections
  • Area P Link
    • Furniture installation to take place
    • Window material delivery, reported to take place
  • Lower Level Area F Dance Studio and Weight Room
    • Punch list and cleaning
  • Area C 3rd level science rooms
    • Seal chemical resistant flooring
    • Fume hood installation
  • Area C 3rd level restrooms
    • Plumbing fixtures
    • Begin ceiling installation
  • New Athletic Corridor/Elevator
    • Continue elevator installation
    • Continue mechanical and electrical rough ins

Centennial Elementary

Completed week ending Friday, October 23, 2020

  • Contractors worked to complete punch list items.
  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems.
  • All-State continued installing security system components.
  • Continued cleaning and flushing the heating and cooling piping system.

Planned week ending Friday, October 30, 2020

  • Contractors to continue working to address punchlist and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.
  • All State to complete building security scope.

Sheridan Hills Elementary

Completed week ending Friday, October 23, 2020

  • Contractors continued working to address punch list items.
  • Continued Phase 2 mechanical piping in the Lower Level.
  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems.
  • All State completed the access control/door security.

Planned week ending Friday, October 30, 2020

  • Contractors to continue to address punchlist and IEA Commissioning log items.
  • Complete the asphalt patching and curb replacement on W. 64th St.
  • Complete excavation for the Chiller Enclosure addition.
  • Begin chiller addition footing and foundations.

Middle School

Completed week ending Friday, October 23, 2020

  • Phase 2 Area D Special Education/Link
    • Restroom tile installation
  • Phase 2 New Conference Room and Staff Lounge
    • Wall painting
  • Phase 2 FACS Lab
    • Mechanical and electrical rough ins
  • Phase 2 Chiller Tower
    • Continued exterior CMU walls
    • Poured transformer concrete pads
  • Phase 3 Third Floor Restrooms
    • Drywall installation continued

Planned week ending Friday, October 30, 2020

  • Phase 2 Area D Special Education/Link
    • Finish ceiling pad installation
    • Restroom plumbing fixtures
  • Phase 2 New Conference Room and Staff Lounge
    • Ceiling grid installation to begin
  • Phase 2 FACS Lab
    • Drywall installation
  • Phase 2 Chiller Tower
    • Chiller piping
    • Finish pouring concrete floor
  • Phase 3 Third Floor Restrooms
    • Drywall installation to continue in south bathroom
    • Start ceiling and tile to start in north bathroom

STEM

Completed week ending Friday, October 23, 2020

  • Furniture punch list items to be delivered and installed

Planned week ending Friday, October 30, 2020

  • Continue testing, balancing, and commissioning of mechanical systems

Dual Language

Completed week ending Friday, October 23, 2020

  • Contractors continued working to address items noted on the commissioning corrective action log.
  • Contractors worked to address issues identified during the 11-month warranty walkthrough.

Planned week ending Friday, October 30, 2020

  • Contractors to continue working to address items noted on the commissioning corrective action log.
  • Contractors to continue working to address issues identified during the 11-month warranty walkthrough.

 

 